Three suppliers quote the same bracket drawing and the top number is nearly twice the bottom. Nobody is lying. The documents price different scopes: one folds the die into the piece price, one bills the die separately, and one never priced the leak test at all.
Almost every large spread reduces to four lines: metal basis, tooling treatment, inspection coverage, packaging boundary. The checks that expose them are the same on every program.
This page audits a document you already have. The general costing method sits in how aluminum die casting prices are calculated; what follows tests whether the numbers in front of you are complete.
A price is a set of assumptions, and the document is where they hide
Two quotes diverge because the assumptions behind them diverge. A casting price is a projection: metal at today’s index, a die life in shots, a yield percentage, a cycle time, an inspection plan. Change one and the number moves without a machine hour changing.
Scoping drives most of it. Casting only, ex works, buyer collects freight, and delivered, inspected, packed in returnable dunnage, can differ widely on the same drawing while both are correct.
Volume comes second. A quote with no stated volume band describes a hypothetical order rather than yours.
Five blocks carry every casting price
Every line item belongs to one of five blocks, and each fails in its own way. Learn the five and a strange quote usually resolves into one of them.
| Block | What sits inside it | What makes it move | What to check in the document |
|---|---|---|---|
| Metal | Shot weight at the alloy price, less metal returned to the furnace | Index, alloy choice, yield assumption | Net and shot weight, index and base date |
| Tooling amortization | Die cost, cavities, life, title | Cavities, die material, slides, life guarantee | Die price, life in shots, ownership, backup die |
| Machining and secondary | Fixtures, CNC time, deburring, coating, assembly | Tolerance band, number of setups, finish standard | Which features are machined, how many setups |
| Scrap, inspection, testing | Yield loss, dimensional reports, X-ray, leak test, cleanliness | Coverage per part or per lot, Cpk target | Which test, at which specification, inside or outside the price |
| Overhead, packaging, freight | Burden rate, dunnage, freight, duty, currency | Incoterm, packaging specification, payment terms | Incoterm and named place, packaging, validity, currency |

Metal and tooling explain most of the spread. Machining and inspection are where scope leaves the document. Freight is where the total surprises you after approval.
Metal is priced on the shot, not on the finished part
The metal line is billed on shot weight, and shot weight is larger than the part. The price starts from everything that solidifies in the die, part plus biscuit, runners and overflow, then credits the metal that returns to the furnace.
That credit is why the gap is smaller than a weight ratio suggests. Die casting returns essentially all in-house scrap to the melt, and the industry design manual puts the net effect at five to ten percent added to material cost rather than the gap the two weights imply. Ask for both weights anyway: 55% and 70% yield on the same part describe different gating, and the difference lands in the piece price.
The metal price is neither yours to fix nor the supplier’s to absorb. USGS puts the average U.S. spot ingot price at 129.5 cents per pound in 2024 and an estimated 180 cents per pound in 2025, a 39% move that will swamp any price built on last year’s metal. A quote with no index, base date or band hides that risk inside the piece price, and it returns as renegotiation or a quietly worse part.
Tooling is capital, and the quote must say who owns it
Tooling is the largest single payment in most programs and the least comparable line, because a die is an asset with a life rather than a cost with a price. NADCA calls die casting tooling among the highest of any production process, and the reason persists at scale: the die runs at metal temperature, takes thermal shock on every shot, and erodes where the melt flows fastest.
Three facts make it comparable: the die cost, the guaranteed life in shots, and who holds title. A die with life N and c cavities delivers N × c parts, so tooling per part is die cost divided by that product. A die price with no stated life is an unknown quantity, and if the same document amortizes a tooling allowance into the piece price, you may pay for one die twice.
Ownership decides the end of the program. A customer-owned die can be moved, refurbished or duplicated; a supplier-owned die has value only inside that relationship. Either is workable, and the document should say which one you are buying.
Twelve fields decide whether a quote can be audited
A quote you can audit states twelve things, and each missing field converts a price into a promise. The list checks in one pass, and a supplier who cannot answer it is telling you something useful.
| Field | What a usable quote states | How to test it |
|---|---|---|
| Drawing revision | The revision the price is based on | A later change should produce a written delta, not a new total |
| Alloy | Grade, plus any temper or modification | Ask what the grade does for elongation on safety parts |
| Net and shot weight | Both, in grams | The ratio exposes the gating and the real metal bill |
| Cavity count | Cavities and the machine the die runs in | Cavities times shots must reach annual volume inside die life |
| Machine band | A tonnage range, not a single press | A part needing a 3050T cell cannot run on a small press |
| Cycle time | Seconds per shot, cooling included | Check it against wall thickness; 4 mm cannot cycle like 2 mm |
| Yield assumption | Good parts as a percentage, and what counts as scrap | Ask what the last three months actually produced |
| Tooling terms | Die cost, life in shots, ownership, backup die | With no life stated the amortization cannot be checked |
| Inspection plan | Test, specification, sampling, and whether it is inside the price | Cross-check each row against the drawing’s acceptance criteria |
| Secondary operations | Each operation named with its standard | Count them; a missing one becomes a change order |
| Packaging and Incoterm | Dunnage, pallet, Incoterm and named place | Add both before comparing two totals |
| Commercial terms | Validity, metal clause, payment terms, minimum quantity | A quote without validity is a price for today only |

None of the twelve is bureaucracy. Shot weight shows whether the metal line is honest, cavity count and machine band whether the piece price can be produced at the quoted rate, and the inspection row tells you which tests you are buying. When the RFQ pack itself is thin the divergence starts upstream, and what OEM buyers must provide before quotation covers those inputs.
Run the amortization arithmetic before comparing prices
Two quotes are comparable only after both are converted to an effective piece price at your real quantity, because the die is a fixed cost wearing a variable cost’s clothes.
The terms:
- D, die cost, one-off, as quoted
- N, guaranteed die life in shots
- c, cavities in the die
- Q, quantity you order while the die is in service
- p, piece price with tooling excluded
Parts from one die: N × c. Tooling per part over die life: D ÷ (N × c). Effective piece price at your volume: p + D ÷ Q.
Break-even follows. Where B carries a higher die cost and a lower piece price, B wins above Q* = (DB − DA) ÷ (pA − pB) and loses below it. One division decides more supplier selections than most negotiations do.
Minimum quantity comes from the same algebra: to keep tooling at or below a share x of contract value, Q ≥ D ÷ (x × p). A supplier who sets a minimum has already chosen an x for you.
Check life too. If D ÷ (N × c) is a meaningful fraction of p while the document claims tooling is included, ask which one it is. Life stated in years cannot be checked against an amortization, which is why shots are the only useful unit.
Levers that move the piece price by double digits
The cheapest savings come from decisions taken before the die is cut, and several move the piece price by ten percent or more without changing the supplier. Each trades a design or commercial freedom for cost, so the question is whether your specification can afford the trade.
| Lever | What changes in the document | What it costs you |
|---|---|---|
| Release as-cast tolerances to an ISO 8062-3 DCTG grade | A machining operation on that face disappears | Less freedom; sealing faces still need machining |
| Move a machined feature into the casting | One operation and one fixture leave the routing | Draft, a witness line, a die that is harder to change |
| Choose a castability-first alloy such as ADC12 or A380 | Lower scrap and a wider process window | Elongation drops to 1–3%, which rules out some crash cases |
| Define a cosmetic boundary on the drawing | Cosmetic rework and full visual inspection come out | Visible faces still meet the drawing; hidden ones stop being arguable |
| Commit to a volume band with a ramp curve | Tooling amortizes over a stated quantity instead of a guess | A shortfall usually carries a true-up clause you must read |
DFM is where these levers get priced. Moving one machined face into the casting can delete a fixture and an operation; relaxing a machined ±0.05 mm callout to a DCTG grade can delete a whole setup. The mechanism, with worked examples, sits in why DFM support saves cost. At quotation time each lever should arrive as a scope change with a number attached.
Four traps that hide inside a low piece price
A low piece price is usually a scope decision made on your behalf. Four traps account for most of the damage, and all four are visible in the fields above.
The low die, high part. A die quoted below cost is recovered through the piece price over the first year. It reads as a bargain until both quotes are converted to effective prices at your volume, and it locks you in: moving the part later means a second die.
Inspection outside the price. A quote covering dimensional inspection but not leak testing, radiographic check or cleanliness reads cheaper until the first lot needs the missing tests as extras. If the drawing calls for a leak test at a stated pressure, medium, hold time and reject limit, that test belongs inside the piece price.
Packaging and freight at the edge of the document. Dunnage, film protection, pallet specification and Incoterm decide whether the number is a part price or a landed price. An ex works price with buyer-arranged freight is legitimate; it is not comparable with a delivered price, and the gap can exceed the piece-price difference under negotiation.
No metal clause, no validity. A price with no index and no expiry will be revisited at the first commodity move, and the revision usually arrives after volumes are committed. The longer version of that pattern is in hidden costs in die casting projects.
Questions buyers ask before comparing two quotes
Four questions come back often enough to answer in one place.
Why is the die quoted separately instead of being built into the piece price?
Because the die is a one-off capital item and the piece price is a rate, and merging them hides both. Separate lines let you compare suppliers on one basis and keep title to an asset you paid for. A supplier who prefers to bundle can still do it; ask for the die cost and the amortization quantity in writing.
How do I compare two quotes with different minimum quantities?
Convert both to an effective piece price at the quantity you will actually order, piece price plus die cost divided by that quantity. When the minimums differ as well, run the break-even formula on the two die costs and the two piece prices, then check that your planned volume lands on the correct side of it.
Does a lower scrap rate always mean a lower price?
No. Yield is one variable among five, and a high yield can be bought with a slower cycle, heavier tooling or extra inspection. Read the yield figure next to the cycle time and the inspection plan; 70% at a long cycle can cost more per good part than 60% at a short one.
What should a metal price clause contain?
An index such as LME or a published regional ingot price, a base date, a band below which nothing changes, and a pass-through formula above it. That makes repricing predictable, and without the band you renegotiate on every order.
Automotive programs tighten the same checklist rather than replacing it. Automotive die casting work carries the tooling, PPAP and inspection expectations a quote has to absorb, and the twelve fields still apply, with less room to negotiate on the inspection row.